v1.2
100 Minories
Guest UserHelpLogout
100 Minories
  • <<
  • MNO12
  • 2022
  • Masonry
  • >>

Basic Interpretation

Context Description

    • Linear brick drain running NW-SE, truncating Cesspool [2010].
      • Chiz Harward
    • 19-5-2016

Record Details

  • Tom Swannick 12-1-2015
  • - - - -
  • - -

Site Photos

  • Site Photo: MNO12_2195
    • file_image
    • Well and drain system
  • Site Photo: MNO12_2196
    • file_image
    • Well and drain system
  • Site Photo: MNO12_2197
    • file_image
    • Well and drain system
  • Site Photo: MNO12_2198
    • file_image
    • Well and drain system
  • Site Photo: MNO12_2224
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2225
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2226
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2227
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2228
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2230
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2232
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2233
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2235
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2236
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2238
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2239
    • file_image
    • Working shot of team excavating and cleaning different sections of the walls and floors of the Georgian buildings 1 and 2 the Crescent.
  • Site Photo: MNO12_2261
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2262
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2263
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2264
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2265
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2266
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2267
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2268
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2269
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2270
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2271
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2272
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2273
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2274
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2275
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2276
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2277
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2278
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2279
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2280
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2281
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2282
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2283
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2284
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2285
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2286
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2289
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2290
    • file_image
    • Cesspool/well and connecting drains
  • Site Photo: MNO12_2323
    • file_image
    • Working shot of the team cleaning and washing back the flooring of the Georgian buildings in preparation for photography.
  • Site Photo: MNO12_2324
    • file_image
    • Working shot of the team cleaning and washing back the flooring of No. 2 The Crescent in preparation for photography.
  • Site Photo: MNO12_2325
    • file_image
    • Working shot of the team cleaning and washing back the flooring of No. 2 The Crescent in preparation for photography.
  • Site Photo: MNO12_2484
    • file_image
    • Drains and rear wall of No 2 The Crescent
  • Site Photo: MNO12_2485
    • file_image
    • Drains and rear wall of No 2 The Crescent
  • Site Photo: MNO12_2556
    • file_image
    • Shot of brick covered drain running North East-South West in the back yard area of No. 2 The Crescent at its extreme Western extent of Area B.
  • Site Photo: MNO12_2558
    • file_image
    • Image showing where a ceramic drain pipe running NE-SW connects two brick covered drains that run NW-SE in the back yard area of No. 2 The Crescent at its extreme Western extent.
  • Site Photo: MNO12_2559
    • file_image
    • Image showing a ceramic drain pipe abutting a brick lined drain that has been purposely blocked in the back yard area of No. 2 The Crescent at its extreme Western edge.
  • Site Photo: MNO12_2560
    • file_image
    • Image showing a ceramic drain pipe abutting a brick lined drain that has been purposely blocked in the back yard area of No. 2 The Crescent at its extreme Western edge.
  • Site Photo: MNO12_2566
    • file_image
    • Truncation of drain 2022 by drain cut 2142
  • Site Photo: MNO12_2567
    • file_image
    • Truncation of drain 2022 by drain cut 2142
  • Site Photo: MNO12_2606
    • file_image
    • Brick Culvert entering Cesspool
  • Site Photo: MNO12_2612
    • file_image
    • Brick Culvert entering Cesspool
  • Site Photo: MNO12_2613
    • file_image
    • Brick Culvert entering Cesspool
  • Site Photo: MNO12_2614
    • file_image
    • Brick Culvert entering Cesspool
  • Site Photo: MNO12_2632
    • file_image
    • Brick Culvert entering Cesspool
  • Site Photo: MNO12_2640
    • file_image
    • Brick Culvert entering Cesspool
  • Site Photo: MNO12_2641
    • file_image
    • Brick Culvert entering Cesspool
  • Site Photo: MNO12_2642
    • file_image
    • Brick Culverts entering Cesspool
  • Site Photo: MNO12_2643
    • file_image
    • Brick Culvert entering Cesspool
  • Site Photo: MNO12_2695
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2696
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2697
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2698
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2699
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2700
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2701
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2702
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2703
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2707
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2708
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2709
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2713
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2714
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2715
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2716
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2717
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2718
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2719
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2720
    • file_image
    • Cesspool and drains interiors
  • Site Photo: MNO12_2721
    • file_image
    • Cesspool and drains interiors

Plan

  • Plan: MNO12_18
    • Top Plan of drainage system in SW corner of Area B

Context Register Text

  • Linear brick drain running NW-SE, truncating Cesspool [2010].

Location

Subgroup

Plan

Section(s)

  • Section: MNO12_44
    • East facing section through drains

Samples

  • No records attached.

Attached Files

  • icon[Download]