v1.2
100 Minories
Guest UserHelpLogout
100 Minories
  • <<
  • MNO12
  • 2323
  • Masonry
  • >>

Basic Interpretation

Stratigraphic Matrix

Context Description

    • Brick sleeper wall front room no 1 the crescent
      • Chiz Harward
    • 20-5-2016

Record Details

  • John Quarrell 23-1-2015
  • - - - -
  • - -

Site Photos

  • Site Photo: MNO12_2863
    • file_image
    • Pole photo of the underfloor construction for the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2864
    • file_image
    • Pole photo of the underfloor construction for the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2865
    • file_image
    • Pole photo of the underfloor construction for the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2866
    • file_image
    • Pole photo of the underfloor construction for the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2867
    • file_image
    • Pole photo of the underfloor construction for the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2868
    • file_image
    • Pole photo of the underfloor construction for the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2869
    • file_image
    • Pole photo of the underfloor construction for the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2896
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot for No. 1 The Crescent.
  • Site Photo: MNO12_2897
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot for No. 1 The Crescent.
  • Site Photo: MNO12_2898
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot for No. 1 The Crescent.
  • Site Photo: MNO12_2899
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot for No. 1 The Crescent.
  • Site Photo: MNO12_2900
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot of No. 1 The Crescent.
  • Site Photo: MNO12_2901
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot of No. 1 The Crescent.
  • Site Photo: MNO12_2902
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot of No. 1 The Crescent.
  • Site Photo: MNO12_2903
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot in the background for No. 1 The Crescent.
  • Site Photo: MNO12_2904
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot in the background for No. 1 The Crescent.
  • Site Photo: MNO12_2905
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot in the background for No. 1 The Crescent.
  • Site Photo: MNO12_2906
    • file_image
    • Brick lined cover for the ceramic drain that ran N-S underneath the flooring of the Northern room and continues into the South Western room which is out of shot in the background for No. 1 The Crescent.
  • Site Photo: MNO12_2962
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2962
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2963
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2963
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2964
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2964
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2965
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2965
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2966
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2966
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2967
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2967
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2968
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2968
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2969
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.
  • Site Photo: MNO12_2969
    • file_image
    • Pole photo showing the underfloor construction and drainage system within the Northern room of No. 1 The Crescent.

Context Register Text

  • Brick sleeper wall front room no 1 the crescent

Location

Subgroup

Plan

Samples

  • No records attached.

Attached Files

  • icon[Download]